Re: Startegy and Package sequence (unregular cycle)

$
0
0

Hi Frazer,

 

In such case

You will have 2 plans:

1st one will be a Strategy plan with unit WEEK as discussed above (without 10 week package) and the

2nd one will be a single cycle plan with 10 weeks frequency.

Start-of Cycle Dates should be matched.

 

Then

You need to take help of user-exit IPRM0002 , the logic written there will be skipping the 9 week trigger.

 

Jogeswara Rao K