Re: Hi experts , after SNP Interactive planning although my available capacity is 8 hr why its showing as capacity level as 90 % , please see the below screen shot and help me .

$
0
0

Hi Rajesh,

 

I think the problem is that you think that the Available Capacity is the Remaining Capacity, and it is not. Available Capacity is making reference to the key figures: Normal Available Capacity, Maximum Available Capacity and Minimum Available Capacity.

Press the botton to close the detail of Available Capacity and you will understand how the % was calculated.

 

Picture.jpg

 

Kind Regards,

Mariano